What is a Section 278 agreement? A practical guide for developers

Footway works behind barriers at a pedestrian crossing, with new tactile paving

A Section 278 agreement is a legal agreement under Section 278 of the Highways Act 1980. It lets a developer fund and carry out permanent changes to the existing public highway, such as a new junction, crossing or road widening, with the consent of the local highway authority.

Section 278 is most often used where a development with planning permission needs those changes. If a scheme needs a new site access, a signalised junction or a footway alteration, none of that work can lawfully begin until the agreement is in place.

That puts the Section 278 on the critical path for most developments that touch the public road. This guide covers what the agreement is, when you need one, how the process runs, what councils in Hertfordshire, Essex and Surrey charge, and how long it takes.

The physical works, the junction build, kerbing, drainage and surfacing, are highway construction in their own right. They are delivered to the highway authority’s specification, and are closely related to the reinstatement work that follows any excavation in the road.

What a Section 278 agreement is, and how it really works

Section 278 sits in Part XIII of the Highways Act 1980, under the heading “agreements as to execution of works”. It lets a highway authority agree with any person that works will be carried out to the highway, with that person paying the cost.

There is one condition: the authority must be satisfied the agreement will be of benefit to the public. So an authority does not have to agree to works simply because a developer is willing to pay for them.

Read literally, the Act has the highway authority carry out the works itself. In practice, the agreement usually lets the developer and their contractor build them on the authority’s behalf, to its standards and under its supervision.

That matters because neither a developer nor a contractor has any right of its own to alter the adopted public highway. The Section 278 agreement is what grants that right.

The current wording of Section 278 dates from the New Roads and Street Works Act 1991. The same Act sets the street works rules covered in the NRSWA Red Book.

Who the highway authority is

The highway authority is whoever maintains the road being altered. Outside London, that is the county or unitary council for most roads, and National Highways for trunk roads and motorways.

In London, the borough council is the highway authority for most roads. Transport for London looks after its own road network, mostly the red routes, and National Highways covers the few motorways.

A site access onto a red route, or a junction where a borough road meets one, can mean dealing with both the borough and Transport for London. Each sets its own charges, so the first job is to confirm who owns every road the works touch.

What “Section 278 works” means

“Section 278 works” is the name for the physical highway works built under a Section 278 agreement. That could be a new junction, bell mouth, crossing, right-turn lane, widened footway or set of traffic signals.

Section 278 works are built to the highway authority’s approved design, by a contractor the authority accepts. They are inspected as they go, because the authority takes them into its own maintenance once they are finished.

On site, the works start with traffic management, because they run alongside live traffic from day one. Then come excavation to the design levels, the sub-base and road base, kerbs set to line and level, and drainage.

The bound surfacing is laid to the Specification for Highway Works. The job is finished with road markings, signs and, where the design calls for them, signals and lighting.

When a Section 278 is required, and whether you need planning permission first

A Section 278 is triggered when a development with planning permission needs changes to a road the public already uses. Typical examples are a new or altered site access, a junction, a roundabout, a right-turn lane, a crossing, footway works, traffic calming or road widening.

The requirement usually arrives as a planning condition that stops the site being occupied until the highway works are delivered. It can also come through a Section 106 obligation to enter into a Section 278 and complete the works to a timetable.

Do you need planning permission first?

In practice, yes. Essex’s highway authority says in its Development Construction Manual that “Evidence of a relevant Planning Consent is required in most cases before the Highway Authority is able to give technical approval”.

Hertfordshire County Council asks for the signed planning decision notice with every Section 278 application. National Highways will not enter into an agreement until permission is in place.

Before permission is granted, a developer can take pre-application advice and get the detailed design ready. That way the application goes in as soon as the decision notice arrives.

Section 278 vs Section 38, Section 106 and Section 184

These four “section” agreements are often confused, partly because they do not all come from the same Act.

  • Section 278 covers alterations to the existing highway.
  • Section 38 covers the adoption of new roads a developer builds inside a site. See our guide to the Section 38 agreement.
  • Section 184 covers vehicle crossings over a footway or verge.
  • Section 106 is not a highways provision at all. It is a planning obligation under Section 106 of the Town and Country Planning Act 1990, used to secure contributions that make a development acceptable in planning terms.

The four agreements compared

AgreementActWhat it coversWho it binds
Section 278Highways Act 1980Alterations to the existing public highwayThe named developer, as a contract
Section 38Highways Act 1980Adoption of new roads built inside a developmentThe named developer, until adoption
Section 184Highways Act 1980Vehicle crossings over a footway or vergeThe frontager or applicant
Section 106Town and Country Planning Act 1990Planning obligations and developer contributionsThe land, binding future owners

Larger schemes routinely need both a Section 278 and a Section 38, and the order matters. The Section 278 junction that ties the site into the existing network often has to be built before the Section 38 estate roads behind it can be connected and adopted.

A council cannot force a developer into a Section 38, because adoption is the developer’s choice. Without one, the estate roads stay private as unadopted roads, maintained by the developer or a management company. A Section 278 is different. If the approved scheme needs work on the existing highway, a Section 278 is the usual, and normally the only practical, route to carry it out.

How the Section 278 process works, step by step

Each highway authority runs its own version of the Section 278 process, but the steps follow the same order. Most of the time goes on the early stages: design approval and the legal agreement.

  1. Talk to the highway authority early. Most authorities offer pre-application advice on the scope of the works and the standards they expect.
  2. Apply. The application goes in with the planning decision notice, land title, a layout and an estimated cost of the works. Hertfordshire charges a £750 non-refundable application fee, then prepares a fee estimate.
  3. Technical submission and review. The detailed design, drainage, construction details, lighting and a Road Safety Audit are checked against the authority’s own design guide. Each set of comments means a resubmission and another review.
  4. Agreement and bond. Once the design has technical approval, the authority’s lawyers draw up the agreement. The developer pays the fees, provides the bond and any commuted sums, and the agreement is signed.
  5. Pre-start requirements. Everything the agreement lists must be in place before work starts, including permits, any traffic orders and a contractor the authority accepts. Technical approval on its own is not permission to start.
  6. Construction under inspection. The authority inspects the works against the approved design, and any change has to be agreed first. A Stage 3 Road Safety Audit is carried out once construction is complete.
  7. Completion and handover. The authority issues a completion certificate and the bond is reduced. A maintenance period follows, commonly 12 months, while the developer puts right any defects. A final certificate then releases the rest of the bond.

What a Section 278 costs: council fees, the bond and commuted sums

A Section 278 is funded entirely by the developer. Section 278(2) of the Act lets the highway authority recover the whole of its costs of making the agreement, of any order the works need, and of any land it has to acquire.

The authority can also recover its administrative expenses, which the Act says include “general staff costs and overheads”. Section 278(3) allows the agreement to include payments towards future maintenance.

In practice, the cost of a Section 278 falls under five headings:

  • the works themselves
  • the authority’s fees for design checks and inspection
  • the authority’s legal costs
  • the bond or cash deposit
  • commuted sums for new features the authority will maintain

Every highway authority sets its own fees, and neighbouring councils charge on different bases. Here is what three councils in McFadden’s area publish.

Published Section 278 charges, checked November 2026

Highway authorityFeesBond or depositAt completion
Hertfordshire County Council£750 application fee (non-refundable), then a fee estimate for the schemeA bond where needed, based on the estimated cost of the worksPart of the bond released at the completion certificate, the rest at the maintenance certificate
Essex County CouncilInspection fee of 8.5% of the works cost (£50,000 to £500,000) or 7.5% (£500,000 to £1.5 million), minimum £1,795.52A bond or deposit covering the full cost of completing the worksDeposit reduced by 90%; maintenance period normally 12 months
Surrey County Council12% of the estimated cost of the works, minimum £2,500 (S278 Guidance Pack)A surety bond, or a cash deposit to the value of the worksSet out in the agreement

Essex also takes an advance checking fee, generally £3,000, and charges legal fees at an hourly rate. Surrey’s 12% applies to a full agreement, with at least half paid at the outset.

The bond

The bond protects the highway authority if the works are left unfinished, for example because the developer goes into liquidation.

A surety bond from a bank or insurer costs the developer a premium rather than the full sum. A cash deposit ties up the full amount. Most authorities reduce the bond once the works are accepted, and hold the balance until the maintenance period ends.

Commuted sums

A commuted sum is a one-off payment towards maintaining features the authority will take on, such as traffic signals, lighting, drainage features or structures. Each authority works it out from its own policy, usually the cost of maintaining and replacing each feature over a set number of years.

The cost of the works

None of these figures is the cost of the works themselves. That depends on the scheme, the ground and the traffic management, and comes from a contractor’s priced quote against the approved design.

In London, each borough and Transport for London sets its own charges. The schedule to ask for is always the one from the authority that owns the road.

How long a Section 278 takes

There is no fixed timescale for a Section 278. It helps to separate two clocks: the time to get the agreement signed, and the time to build and hand over the works.

Getting the agreement signed

Hertfordshire County Council recommends that developers “allow 10-16 weeks after payment of the fee estimate to the completion of a Section 278 Agreement”. Those weeks run from paying the fee estimate, which follows the application, so the time from first submission is longer.

Where a road closure is needed, Hertfordshire says to allow at least 16 weeks for the traffic order.

The design moves this clock most. Every round of comments means another review, and Road Safety Audit responses, traffic orders and the legal work all add time.

Building and handing over the works

The build clock starts once the agreement is signed. Road space has to be booked, and Surrey warns that a permit application “may need to be submitted at least 3 months in advance of the intended start date”.

Where a council runs a lane rental scheme, a daily charge applies to works on its designated streets at the busiest times. Construction follows, then a maintenance period of commonly 12 months before the final certificate.

Start early, within the rules

Highway authorities generally will not take a formal Section 278 application until planning permission is granted. But pre-application advice, the detailed design and the Road Safety Audit work can all be moving while the planning application is decided.

A complete, checked design submitted the week permission is granted takes the most time out of the critical path.

Choosing a contractor for the highway works

The highway authority decides who can work on its roads. Hertfordshire’s rule is direct: “Work on the public highway can only be undertaken by a contractor on our Accredited Contractor List”.

To join that list, a contractor needs at least £10 million of public liability cover and references. Surrey’s guidance says developers can ask which contractors the council approves once the estimated value of the work is known. Checking this before tender avoids a late change of contractor.

A Section 278 rarely stands alone. It sits alongside the site civils, the Section 38 roads, the drainage and any utility diversions, and the interfaces between them are where programmes slip. When those workstreams sit with separate contractors, each interface needs an owner from day one.

McFadden Utilities has the teams capable of delivering Section 278 highway works and is structuring its delivery for them. Day to day, McFadden carries out highway reinstatement and surfacing to the highway authority’s specification across Hertfordshire and the surrounding counties.

Frequently asked

Questions on the Section 278 agreement

A Section 278 agreement covers alterations to the existing public highway, such as a new junction or crossing needed to serve a development. A Section 38 agreement covers the adoption of new roads a developer builds inside a site and hands over to the highway authority to maintain. Both come from the Highways Act 1980, and larger schemes often need both, with the Section 278 works usually built before the Section 38 roads behind them can connect.

The developer pays for everything: the works, the highway authority’s fees and legal costs, a bond or cash deposit, and commuted sums for new features the authority will maintain. Fees vary by authority. Surrey charges an agreement fee of 12% of the estimated cost of the works on a full agreement (minimum £2,500), Essex an inspection fee of 8.5% for works between £50,000 and £500,000, and Hertfordshire a £750 application fee followed by a fee estimate for each scheme. The cost of the works themselves depends on the scheme and comes from a contractor’s quote.

There is no fixed timescale. Hertfordshire County Council recommends allowing 10 to 16 weeks from paying its fee estimate to a completed agreement, and at least 16 weeks for the traffic order where a road closure is needed. That clock starts after the application, and construction and a maintenance period, commonly 12 months, follow once the agreement is signed. The quality of the design and the number of review rounds make the biggest difference.

In practice, yes. Highway authorities generally will not take a formal Section 278 application, or give technical approval, until planning permission is granted. Essex needs evidence of planning consent in most cases before technical approval, Hertfordshire asks for the signed decision notice with the application, and National Highways will not enter into an agreement without permission in place. Pre-application advice and design work can start earlier.

Not in the way a Section 106 obligation does. A Section 278 is a contract with the named developer, so the obligation to build the works does not pass automatically if the site or a plot is sold. But if money due under the agreement is not paid, Section 278(5) of the Highways Act lets the highway authority stop the access being used, recover the sum from anyone with an interest in the land the access serves, and declare it a charge on that land.

A contractor the highway authority accepts to work on its network. Some authorities keep a formal list: in Hertfordshire, work on the public highway can only be carried out by a contractor on the county council’s Accredited Contractor List. Others, such as Surrey, say developers can ask which contractors they approve. The works are built to the authority’s approved design and inspected as they go.

Share
PM
About the Author

Paul McFadden

Paul is the director of McFadden Utilities Limited, a family-run water utility and civils contractor based in Welwyn Garden City, Hertfordshire. With over 20 years in the water industry, Paul oversees all self-lay, main laying, and repair and maintenance operations across London and the South East.

View all posts by Paul →
More about this service

Reinstatement and highway surfacing

Groundworks, surfacing to specification and reinstatement a highway authority will accept are everyday work for our team. See how we deliver highway reinstatement and surfacing across Hertfordshire and the surrounding counties.

Explore reinstatement works →
Get In Touch

Got a project
to discuss?

40 years of getting it done, one phone call away.

Request a quote