How long does tarmac take to dry? What the standards say, and why it depends on the material

cold lay 2

Hot-laid tarmac does not dry. It cools, and it is ready for traffic once it has cooled, so the honest answer to how long tarmac takes to dry is hours rather than days on most jobs. The three to five days most people are told to wait is either cautious advice for a domestic driveway or a description of cold applied material, which is a different product that genuinely does take time to set.

The short answer is not the whole story, because the two materials behave in opposite ways in the weather and the standards treat them differently. This guide sets out what “dry” actually means, what the UK highway specification says about when a surface can be opened, why a road reinstatement reopens the same day, and why a driveway installer is still right to tell a customer to wait.

McFadden’s tarmac road surfacing crews lay hot asphalt to the highway specification on car parks, access roads and reinstatements, and switch to cold applied when the weather closes the window, so this is written from the contractor’s side of the job.

Hot-laid tarmac does not dry. It cools, and once it is cool it is ready.

What “dry” actually means

When people ask how long tarmac takes to dry they are asking about one of four different things, and a single number cannot cover all four.

Four things people mean by dry

What you are waiting forWhat is actually happeningHow longWhich material
CoolingHot-laid asphalt goes down at over 150°C and hardens as it loses heat. There is no water in it to evaporateHoursHot lay
SettingA small amount of flux oil in the mix has to go off before the surface firms upHours to days, depending on product, compaction and weatherCold applied, sold in bags as cold lay
AgeingThe bitumen keeps stiffening slowly for months as it oxidisesMonths, and nothing to do with when you can use the surfaceBoth
CautionA fresh, thin surface marks under a power-steering scrub or a caravan leg even once it is coolDays, to protect the finishBoth, driveways especially

The “six months to fully cure” that gets passed around is ageing. It is real, and it changes nothing about when the surface can take a car.

Hot-laid tarmac: it cools, it doesn’t dry

The UK highway specification does not give a drying time at all. It gives a temperature. Under the Manual of Contract Documents for Highway Works, Series 900, a newly surfaced road “shall not be opened to traffic if its surface temperature exceeds 25°C unless the maximum temperature within the mat has fallen below 35°C”, measured in the middle of the layer. Cool enough, open. That is the rule every motorway and A-road is surfaced to, and the laying temperatures behind it come from BS 594987.

MCHW Series 900, hot-laid asphalt
Minimum delivery temperature
155°C
Compaction substantially complete
Before the mat falls below 120°C
Open to traffic
Mat below 35°C mid-layer, or surface below 25°C
Minimum air temperature for laying
0°C, never on a frozen substrate
Maximum wind for laying
40 km/h measured at 2 m

Laying hot asphalt is a race against cooling, and how long the race lasts depends mostly on thickness. The notes for guidance say layers of 50 mm and over are "tolerant of all but the most extreme conditions encountered in the UK", while thinner layers are at the mercy of air temperature "and, more particularly, wind".

Thickness is why a thin driveway surface course is cool enough to stand on within hours and drive on the same day, while a thicker binder course on a road holds its heat for longer. Thickness and cooling are also why a highway reinstatement can be trafficked before the crew has left. The Specification for the Reinstatement of Openings in Highways defines interim reinstatement as work completed "before opening the works to traffic". Nobody closes the A1 for three days over a two-metre trench.

Cold applied tarmac: it sets, on its own schedule

Cold applied asphalt is a different material with a different clock. It is mixed with a flux oil so it stays workable at ambient temperature, and it firms up as the flux evaporates. There is no temperature to wait for. There is a process to wait for, and the manufacturers will not put a number on it.

Tarmac's own technical data sheet for its cold lay macadam says the time to harden fully "will depend on the degree of compaction and ambient temperature", and leaves it there. The same sheet says not to use it below 5°C or on a very wet surface, that it "may be prone to marking during early life and warm conditions", and to "protect from caravan legs, jockey wheels and other similar high loadings". Hanson's data sheet for its equivalent says the product is not suitable for heavily trafficked areas or "areas exposed to high stress such as turning". Read together, the manufacturers' honest answer is that cold applied will take a light car once compacted, it will mark for days, and it wants warmth to finish.

The point most people get wrong about cold applied is that it is only a temporary patch. It is not. Appendix A2.4 of the SROH permits Permanent Cold-lay Surfacing Materials with a current HAPAS certificate at any position in footways, footpaths and cycle tracks, and as binder and surface course in Type 3 and 4 roads. The bag from the merchant is a deferred set mixture, which the same specification uses as the interim material, tuned to "approximately the equivalent to 10 days deferred set". Both are cold applied. They are not the same product, and the permanent one is what a reinstatement contractor lays when the weather has closed the hot-lay window. Our SROH guide covers the specification itself.

Timings by material and by use

When new tarmac can take load

UseHot-laid asphaltCold applied (bagged deferred set)
Walk onOnce cool to the touch, typically within hoursOnce compacted; avoid sharp heels and dragging anything across it
Drive onOnce the mat is below 35°C mid-layer, usually the same dayLight vehicles once compacted; do not turn the wheels while stationary
Park onSame day once cool; avoid one spot for the first day or two in warm weatherNot for days; point loads mark it until the flux has gone off
HGVs and turningOnce cool, on a pavement designed for itNot suitable for bagged products, per the manufacturers

The hot-lay timings come from the specification. The cold applied timings are manufacturer guidance, because there is no specification figure to give.

Weather, and which way it pushes

Weather affects both materials, in opposite directions, and the two are often confused.

What the weather does to each material

ConditionHot-laid asphaltCold applied
ColdA laying problem, not a drying one. The mat cools faster, so there is less time to compact before it drops below 120°C, and the specification stops laying below 0°C or in wind above 40 km/h. Once laid, cold weather makes it trafficable soonerSlows the flux going off, so the surface stays soft for longer. Below 5°C the manufacturer says not to lay it at all
HeatThe one condition that genuinely delays opening, because the mat cools slowly and the 25°C surface rule takes longer to meet. A thick layer laid on a hot afternoon may not open until the eveningSets faster, and marks more easily while it does. Point loads and turning wheels are the risk on a warm day
RainA laying problem. The specification does not allow laying where standing water is present, and rain on a hot mat cools it too fast to compact properly. Rain on a surface that has already cooled does nothing to itA very wet surface stops the material bonding, so it should not be laid on one. Rain after compaction does not stop the set, though it does nothing to speed it

Why the road reopens in an hour and your driveway installer says five days

The road crew and the driveway installer are both right. A utility reinstatement in a carriageway is laid to the highway specification, thick enough to hold its heat and compacted to a measured standard, and it opens on the temperature rule because the alternative is a closed road. Nobody parks on it with the wheels on full lock.

A driveway is a thin surface course that will have the same car parked on the same spot every evening, turned on the spot, with jockey wheels and bike stands and the occasional skip. It is cool in hours. The installer's five days is about letting the surface toughen before it takes that punishment and, on a cold applied driveway, about giving the flux time to go off. Follow it. It is protecting the finish, not waiting for the tarmac to dry.

A surface that is still soft after a week is the difference between the two materials showing itself. A hot-laid surface that stays soft was laid thin, laid too cool to compact, or laid on a poor base, and needs looking at. A cold applied surface that stays soft is

Frequently asked

Questions on this topic

Hot-laid tarmac does not dry, it cools, and it is ready once cool, usually within hours. The UK highway specification opens a road to traffic once the mat is below 35°C mid-layer or the surface is below 25°C. Cold applied tarmac sets rather than cools and the manufacturers give no fixed time, because it depends on compaction and temperature.

For hot-laid tarmac, the same day, once the mat has cooled to the specification temperature. For cold applied, light vehicles once it is properly compacted, but avoid turning the wheels while stationary and avoid parking in one spot until the surface has firmed up.

There is no fixed figure. Tarmac’s data sheet says the time to harden fully depends on the degree of compaction and ambient temperature. Cold weather slows it, warm weather speeds it, and the surface is prone to marking under point loads in its early life. Manufacturers advise against laying it below 5°C.

Hot lay should not be laid on standing water or in rain, because rain cools the mat too quickly to compact properly. Cold applied should not be laid on a very wet surface because it will not bond. Rain falling on either material after it has cooled or been compacted does not damage it.

Longer than in cool weather, for hot lay. The mat loses heat more slowly, so it takes longer to reach the 25°C surface or 35°C mid-layer temperature at which the specification allows it to open. A thick layer laid on a hot afternoon may not open until the evening. Cold applied sets faster in heat but marks more easily.

If the tarmac is hot lay and has already cooled, nothing. If it is still hot, rain can cool it before compaction is complete, which is why contractors do not lay in rain. If it is cold applied and freshly compacted, a shower will not stop it setting, but standing water on the surface before laying will stop it bonding.

Share
PM
About the Author

Paul McFadden

Paul is the director of McFadden Utilities Limited, a family-run water utility and civils contractor based in Welwyn Garden City, Hertfordshire. With over 20 years in the water industry, Paul oversees all self-lay, main laying, and repair and maintenance operations across London and the South East.

View all posts by Paul →
More about this service

Tarmac road surfacing

McFadden Utilities lays hot rolled asphalt and cold applied surfacing for car parks, access roads and utility reinstatements across Hertfordshire, London and the South East, to the highway specification.